Getting Started - Webasto PosiCharge SVS100N Operation And Maintenance Manual

Gse intelligent fast charging systems
Table of Contents

Advertisement

Getting Started

1
Before you begin, take the time to familiarize yourself with the Cautions in Section 2, and read
the Installation Instructions in Section 4 completely before you install your new SVS100N.
To get your system up and running quickly perform the following steps:
1. Ensure the SVS100N siting requirements are followed. (Section 4.1 and 4.2)
2. Connect the 3 phase utility power to the SVS100N, and apply power to the SVS100N.
(Section 4.7)
3. Install the BMID. (Section 3)
4. Once BMID is installed, the battery pack may be connected to the charger.
5. If your BMID does not come pre-configured, you will need to initialize and program the new
BMID. (Refer to BMID programming Manual, document #06701-W-03)
6. Once the BMID has been programmed, the battery pack is ready to begin charging.
12876-W-03-01
SVS100N Operation/Maintenance Manual
1
Webasto Charging Systems, Inc.

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

12877

Table of Contents