3.3.6
Turning the housing
After mounting, the housing can be turned 350° in order to ease access to the display and the
terminal compartment. Proceed as follows to turn the housing to the required position:
• Undo the fixing screw (1)
• Turn the housing (2) in the required direction
• Tighten the fixing screw (1).
F12/F23 housing
2
1
3.4

Post-installation check

After the measuring device has been installed, perform the following checks:
• Is the device damaged (visual inspection)?
• Does the device correspond to specifications at the measuring point, including process
temperature and pressure, ambient temperature, measuring range, etc.?
• Are the measuring point number and labeling correct (visual inspection)?
• Is the device adequately protected against rain and direct sunlight (→ ä 78)?
Levelflex M FMP43 with FOUNDATION Fieldbus
T12 housing
2
1
allen key
4 mm/0.1"
L00-FMP41Cxx-17-00-00-en-002
Endress+Hauser

Advertisement

Table of Contents
loading

Table of Contents