ECC800 Data Center Controller
User Manual
Procedure
Step 1 Install cables between the fire controller and ECC800-Pro.
Figure 6-76 Installing cables between the fire controller and ECC800-Pro
Step 2 Log in to the ECC800-Pro WebUI as an administrator.
Step 3 Choose System Settings > Linkage Control.
Step 4 Ensure that Enable linkage control function is Yes.
Step 5 On the Linkage Group tab page, set Link fire control with air conditioner off to
on.
Select Link fire control with air conditioner off under Linkage Group. If its value is on, the
corresponding logic configurations under Linkage Logic List are available. If its value is off, the
corresponding logic configurations under Linkage Logic List are unavailable.
Step 6 Modify the AI/DI_3 signal name.
1.
2.
3.
4.
Step 7 Enable the AI/DI device.
1.
2.
3.
Issue 04 (2021-10-09)
NO TE
Log in to the ECC800-Pro WebUI as an administrator.
Choose System Settings > Signal Name Modify. The Batch Signal
Configuration page is displayed.
Set Device type to ECC800, set Device name to ECC800, and click OK.
On the query result tab page, set the new signal name of AI/DI_3 to Fire and
click Submit.
Choose Monitoring > System > ECC800 > Running Parameters > AI/DI_3
Port Settings.
Set Fire sensor to Enable. Click Submit to access the AI/DI_3 setting page.
Select Fire sensor type and set it to Normal Open or Normal Close as
required.
Copyright © Huawei Technologies Co., Ltd.
6 Feature Description
214

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

Ecc800

Table of Contents