Weekly
Instrument/Component
Maintenance
Liquid handling arm,
Robotic manipulator arm,
Air displacement
pipetting arm (Air LiHa)
The weekly maintenance should be performed on the last working day of each week.

9.2.4 Maintenance Table: Yearly Maintenance

Annual maintenance will be performed by a Lonza approved FAS (field application specialist)
and be offered through a service contract. Reference material for the maintenance tasks
can be available upon request.
Every Twelve
Instrument/Component
Months
Air displacement pipetting
arm (Air LiHa)
Complete PyroTec™ PRO
Frontal arm guide
Worktable
LiHa
LiHa; support tubing
DiTi cone and tubing ex-
tension
Air LiHa; DiTi cone tip
adapter
RoMa
RoMa; Z-rod
Complete PyroTec™ PRO
PyroTec™ PRO Hardw are User's Manual, V1.2
Maintenance Task
Clean front arm guide
Perform the following tests:
• Pressure Leak Test
Maintenance Task
Perform liquid handling
performance verification test
(Colorimetric QC Kit test or Gravimetric test)
Clean system
Clean
Visually inspect worktable grids for wear and replace
if necessary.
Visually inspect moving parts, especially Y-belt and lower DiTi eject
option, for wear and replace faulty parts.
Check parts for abrasion; wipe wear debris off, if necessary.
Check condition of mesh (must not be broken).
Check if support-tubing ends lock firmly in their seats.
Replace defective support tubing.
Replace
Replace option DiTi cone Air LiHa
Visually inspect moving parts, especially Y-belt, for wear and replace
faulty parts.
Check parts for abrasion; wipe wear debris off, if necessary.
Clean
Perform tests according to form "Preventive Maintenance"
Return to TOC
Reference
See section "Arm Guide"
See PyroTec™ PRO Software
User Guide
RT-MN024-1.2 02/21
86

Hide quick links:

Advertisement

Table of Contents
loading
Need help?

Need help?

Do you have a question about the PyroTec PRO and is the answer not in the manual?

Table of Contents