NetCol5000-A025 In-row Air Cooled Smart Cooling
Product
User Manual (300 mm Width)
Figure 4-36 Startup wizard
Step 2 Tap Yes. The checking before startup screen is displayed, as shown in
If the remaining refrigerant is not charged, tap No. Complete refrigerant charging,
and then perform the wizard commissioning.
Figure 4-37 Checking before startup
Step 3 Tap Yes for check items one by one according to the prompt messages on the
screen.
Step 4 Tap Yes and enter the screen where you select commissioning items, as shown in
Figure
Issue 15 (2020-12-10)
NO TE
● For the initial startup wizard, Last record is in gray, indicating that the operation is not
allowed.
● For the non-initial startup wizard, choose Last record and you can view the last startup
wizard report.
NO TICE
4-38.
Copyright © Huawei Technologies Co., Ltd.
4 Power-On Commissioning
Figure
4-37.
162