6.2

Change of Operation Status (RUN/STOP)

You may use RUN/STOP/MODE switch operations to change the C Controller module operation status (RUN/STOP).
For details of the operation status, refer to the following.
 Page 307, Section 17.2.3 RUN, STOP and PAUSE status operation processing
● Changing the operation status (RUN/STOP/PAUSE) also changes output from the user program.
For details, refer to the following.
 Page 151, Section 11.1.5 Output (Y) status setting for switching STOP to RUN
● When the operation status is STOP/PAUSE, the user program task does not stop.
● For the remote operation, refer to the following.
 Page 163, Section 11.5 Remote Operation Function
(1) Operating procedure
Switch operations are described below.
(a) RUN
<Q24DHCCPU-V/-VG/-LS><Q26DHCCPU-LS>
<Q12DCCPU-V>
(b) STOP
<Q24DHCCPU-V/-VG/-LS><Q26DHCCPU-LS>
<Q12DCCPU-V>
70
1.
Move the RUN/STOP/MODE switch to the RUN position.
Q24DHCCPU-V/-VG/-LS and Q26DHCCPU-LS···RUN LED is
lit green.
Q12DCCPU-V···RUN LED is lit orange.
1.
Move the RUN/STOP/MODE switch to the STOP position.
RUN LED goes off.