Procedure to determine what has caused the insulation fault:
cumplimiento será denunciado por daños y perjuicios. Todos los derechos están reservados, incluyendo
1.- Disconnect the solar panel circuit from the inverter.
aquellos que resulten de derechos de patentes o registro del diseño.
2.- Open the inverter, taking the safety warnings in this section into account and treating the operation as handling,
with which that laid down for handling operations in Section 4 will apply.
La correspondencia del contenido del documento con el hardware ha sido comprobada. Sin embargo,
3.- Remove the varistors.
pueden existir discrepancias. No se asume ninguna responsabilidad por la concordancia total. La infor-
4.- Check with a multimeter that there is high impedance in the varistor terminals and continuity in the thermal fuse
terminals. If this is not the case, the varistor or thermal fuse which does not pass the check above will need to be
mación que contiene este documento es revisada regularmente y es posible que se produzcan cambios
replaced.
en siguientes ediciones.
El presente documento es susceptible de ser cambiado.
The copy, distribution or use of this document or of its content requires written authorisation. Any
breach thereof will be reported for damages. All rights reserved including those of patent rights or
design registration.
The conformity of the document content with the hardware described has been checked. However,
discrepancies may exist. Liability will not be assumed for total concordance. The information contained
in this document is regularly revised and it is possible that there may be changes in subsequent
5.- If the problem persists and the check is correct, contact Ingeteam Energy S.A.
editions.Other functions may be available which are not covered by this document.
6.- Correctly insert the three varistors before closing the unit.
This document may be changed.

8.1.3 Red LED

This is the continuously lit LED indicating that the inverter is manually stopped.
To start it up, this must be done manually, as the START or STOP condition does not change even when the unit
loses power.
In the main menu, highlight the START/STOP option and
press
to toggle the status.
OK
The display shows the following message:
Highlight the desired option again and press
Page 2
Page 44
44
1 2 3 fusible
3 fusible
2
1
1
3 fusible
12:00
Start / Stop
Partial Data Reset
Change inverter number
Other adjustments
12:00
ON / OFF
OK
.
Change to Stop (OK)
Cancel (ESC)
Manual de instalación
Installation Manual
INGECON® SUN LITE
INGECON® SUN LITE
AAY2000IKH01
MAIN MENU
AAY2000IKH01
Fecha: Marzo 2011
Date: March 2011
AAY2000IKI01
12/04/10
09/01/09
AAY2000IKI01
Rev. _B
Rev. _B

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents