Placing And Connecting Cabling - Raven SBGuidance Onland Plough Installation Manual

Table of Contents

Advertisement

SBGuidance Onland Plough I Version 1.3 I CAN

2.7. Placing and connecting cabling

An Implement Ready cable harness is required
on the tractor for connecting the Onland plough
steering. The IBBC connector ensures that
connection (Figure 16).
Section 2.8 shows a schematic view of the
cable connecting circuit. The CAN implement
lead ensures that the STU is connected to the
tractor. In addition, the hydraulic harness needs
to be connected to the STU. This hydraulic
harness ensures the control of the hydraulic
valve and the readout of the sensors.
For an easy installation of cabling use the
hydraulic hoses already present on the plough
as a guide. Figure 17 shows an example where
the cabling is mounted using protective tubing
for the cables and pipe clamps for fixation.
Mount the CAN implement harness in
such a way that the separate conductors
coming from the protective sleeve are
directed downwards. This will prevent
any penetration of water into the
protective sleeve.
Ensure that the leads are not damaged
when installed.
Figure 16 IBBC bracket with connector
Figure 17 Guiding of cabling
SBG-Onland-Plough-IM-EN-V1.3 I Pag 21/39

Advertisement

Table of Contents
loading

Table of Contents