1. Installation
1.2.2 Setting the CPV Direct
Festo P.BE-CP-DI01-EN en 0007a
When the switch module has been removed, you will see two
DIL switches in it (Fig. 1/3).
You can set the following parameters with the DIL switches:
–
the field bus protocol
–
the extension to the CP system
–
the station number
–
the diagnostic mode
Proceed as follows:
1. Switch off the operating voltage.
2. Remove the switch module (chapter 1.2.1).
3. Set the field bus protocol (4-position DIL switch, elements
1...2).
4. Set the extension to the CP system (4-position DIL switch,
elements 3...4).
5. Assign an unused station number to the CPV Direct. Set
the desired station number (8-position DIL switch,
elements 1...7).
6. Set the diagnostic mode (8-position DIL switch, element 8).
7. Fit the switch module (chapter 1.2.1).
1-7