2. Commissioning PROFIBUS-DP
Festo P.BE-CP-DI01-EN en 0007a
Recommendation:
Providing the safety concept of your machine/system per-
mits, commission the CP system with both operating voltages
(pins 1 and 2), but without compressed air. You therefore
have a suitable test function which does not trigger undesired
reactions.
Please note
A CP valve location occupies two addresses.
The following applies:
– lower-value address:
– higher-value address:
pilot solenoid 14
pilot solenoid 12
2-27