P05 - Changeover

P05
Designation on ATC
display
Changeo-
ver
P05.01
Application type
P05.02
Priority line
P05.03
Line 1 -> 2 interlock
P05.04
Line 1 -> 2 interlock
P05.05
Changeover re-
sponse
P05.06
Feedback delay
3KC ATC6300 transfer control device
Manual, 03/2018, L1V30535632002A-01
Description
Type of application
– This parameter specifies the type of applica-
tion and facilitates the management of the cor-
responding input / output signals.
U-G = Utility (network) / Generator
U-U = Utility (network) / Utility (network)
G-G = Generator / Generator
Selecting the priority line
– Specifies the priority line. It defines the line
through which the loads are supplied, if both
lines are present.
Line 1 → Line 2 interlock time
– Delay that elapses between the disconnection
of breaker Line 1 and the opening command for
breaker Line 2. For example, if the breaker Line
1 is opened, there is a wait time of 6 seconds in
accordance with default settings for an opening
command to be sent to the breaker Line 2.
Line 1 ← Line 2 interlock time
– Delay that elapses between the disconnection
of breaker Line 2 and the opening command for
breaker Line 1.
Changeover response
– This parameter defines the general conditions
for a changeover.
A selection can be made between OBP (Open
before presence) and OAP (Open after pres-
ence).
Maximum time for switch control -
Alarm delay A03 – A04
– If a switching device is not in the correct posi-
tion within this time following an ON or OFF
command, alarm A03 or A04 is triggered.
For more detailed information on the alarms,
please refer to chapter Alarms (Page 46).
Parameterization
9.3 Parameters
Unit
Default
Range
U-G
U-G
U-U
G-G
- 1 -
-1- Line 1
-2- Line 2
s
6.0
0.1 ... 1800.0
s
6.0
0.1 ... 1800.0
OBP
OBP
OAP
s
5
1 ... 900
1)
2)
125