2. Commissioning
Fig. 2/12: Assignment of the process data to the variables of the PLC by drag & drop
2−22
Assignment of the process data
1. For assignment of the process data, change into the
Process Data Workspace": Menu [View] [Process Data]
or with the symbol shown to the left.
In the Process Data Assignment" window, below the
Symbols/Variables" tab, the folder STD_RES is
displayed in the directory tree (see fig. left).
2. Click on Default" in the folder STD_RES".
The newly created variables are displayed below the
window.
3. In the right window (shows the hardware/bus structure)
under PROFINET, click on the element EA64: ".
The process data of the CPX−SF34/35 are displayed
below the window.
4. Pull the process data of the right window into the left
window onto the lines of the variables (marked
individually or jointly, see Fig. 2/12).
This assigns the process data of the CPX−SF34/35 to the
variables of the PLC. In the next section, you will find
programs for communication between the PLC and
CPX−SF34/35.
Festo P.BE−CPX−SF34+SF35−E N en 1007NH