Installation Checklist - Eaton IBC-L Installation Manuals

93pm integrated battery cabinet-large and large high rate
Hide thumbs Also See for IBC-L:
Table of Contents

Advertisement

Installation
9.
Connect the thermal sensor interface wiring to the IBC thermal sensor interface terminals. See paragraph
3.2.2 IBC Power Wiring Preparation
For a detailed view of the IBC terminal block, see
10. Connect the thermal sensor interface wiring to the UPS thermal sensor interface (building alarm) terminals.
Refer to the applicable Eaton 93PM UPS Installation and Operation manual listed in paragraph
1.7 For More
NOTE
11. Reinstall the internal safety shield panel removed in
4.3.1 Line-Up-and-Match Power
12. Close the outside door and secure the latch.
13. If removed, reinstall the sidecar internal safety shield panel and secure with the retained hardware.
14. If removed, reinstall the sidecar front panel and secure with the retained hardware.
15. Once the battery cabinets are installed and wired, return to the applicable Eaton 93PM UPS Installation and
Operation manual, listed in paragraph
4 4 . . 6 6
I I n n i i t t i i a a l l S S t t a a r r t t u u p p
Startup and operational checks must be performed by an authorized Eaton Customer Service Engineer, or the
warranty terms specified in
contract for the UPS. Contact an Eaton service representative in advance (a minimum two-week notice is
required) to reserve a preferred startup date.
4 4 . . 7 7
C C o o m m p p l l e e t t i i n n g g t t h h e e I I n n s s t t a a l l l l a a t t i i o o n n C C h h e e c c k k l l i i s s t t
The final step in installing the IBC is completing the following Installation Checklist. This checklist ensures that
you have completely installed all hardware, cables, and other equipment. Complete all items listed on the
checklist to ensure a smooth installation. Make a copy of the Installation Checklist before filling it out, and
retain the original.
After the installation is complete, an Eaton Customer Service Engineer must verify the operation of the UPS
system and commission it to support the critical load. The service representative cannot perform any
installation tasks other than verifying software and operating setup parameters. Service personnel may request
a copy of the completed Installation Checklist to verify all applicable equipment installations have been
completed.
NOTE
60
Eaton 93PM Integrated Battery Cabinet (IBC-L, IBC-LH [432V], and IBC-LH [480V]) Installation Manual 164000228—Rev 08
and
Table 12
Information, for UPS cabinet termination requirements.
In the following step, if the safety shield cannot be reinstalled because of misalignment,
use the leveling feet to realign the cabinet.
Wiring.
1.7 For More
Chapter 8 Warranty
The Installation Checklist MUST be completed prior to starting the UPS system for the
first time.
for termination requirements.
Figure 30
or
Figure
31.
Step 3
of paragraph
Information, to complete the UPS wiring.
become void. This service is offered as part of the sales

Advertisement

Table of Contents
loading

This manual is also suitable for:

Ibc-lh93pm ibc-l93pm ibc-lh

Table of Contents