Installation Plan and Unpacking
Because of the battery shunt trip wiring route in the 93PM UPS cabinet, the wiring from the IBC to the
UPS must use wire rated for 600V and Class 1 wiring methods.
The battery detect signal wiring from the battery cabinet must be connected to a programmed UPS
building alarm.
Battery detect and 48 Vdc shunt trip wiring should be a minimum of 18 AWG.
Use twisted-pair wires for each input and return or common.
All interface wiring and conduit is to be supplied by the customer.
Interface wiring can be installed using the inter-cabinet wiring access pass-through or by routing wiring
through conduit between cabinets.
Install the interface wiring in separate conduit from the power wiring.
3 3 . . 3 3
I I n n s s p p e e c c t t i i n n g g a a n n d d U U n n p p a a c c k k i i n n g g t t h h e e I I B B C C
The cabinet is shipped bolted to a metal and wood pallet (see
protective packaging material.
NOTE
The IBC is heavy (see
may tip and cause serious injury or death.
1.
Carefully inspect the outer packaging for evidence of damage during transit.
Do not install a damaged cabinet. Report any damage to the carrier and contact an Eaton service representative
immediately.
NOTE
2.
Use a forklift or pallet jack to move the packaged cabinet to the installation site, or as close as possible,
before unpacking. If possible, move the cabinet using the pallet. Insert the forklift or pallet jack forks
between the supports on the bottom of the pallet. See
gravity measurements.
Do not tilt the more than 10° from vertical or the cabinets may tip over and cause serious injury or death.
3.
Set the pallet on a firm, level surface, allowing a minimum clearance of 3m (10 ft) on each side for
removing the cabinet from the pallet.
4.
Remove the protective packaging material from the cabinet and recycle in a responsible manner. Retain
the parts kit box packed at the top of the cabinet.
28
Eaton 93PM Integrated Battery Cabinet (IBC-L, IBC-LH [432V], and IBC-LH [480V]) Installation Manual 164000228—Rev 08
Startup and operational checks must be performed by an authorized Eaton Customer
Service Engineer, or the warranty terms specified in
This service is offered as part of the sales contract for the UPS. Contact an Eaton service
representative in advance (usually a two-week notice is required) to reserve a preferred
startup date.
Table
1). If unpacking and unloading instructions are not closely followed, the cabinet
For the following step, verify that the forklift or pallet jack is rated to handle the weight
of the cabinet (see
Table 1
Figure 10
or
Figure
Chapter 8 Warranty
WARNING
CAUTION
for cabinet weight).
Figure 8
or
Figure 9
CAUTION
11), and covered with outer
become void.
for the IBC-L cabinet center of

Advertisement

Table of Contents
loading

This manual is also suitable for:

Ibc-lh93pm ibc-l93pm ibc-lh

Table of Contents