Installation
4 4 . . 8 8
I I n n s s t t a a l l l l a a t t i i o o n n C C h h e e c c k k l l i i s s t t
o All IBCs are the same model and rating.
o All packing materials and restraints have been removed from each cabinet.
o The IBCs are installed on a level floor suitable for computer or electronic equipment.
o The IBCs are placed in their installed location
o All conduits and cables are properly routed between the IBCs and the UPS.
o All power cables are properly sized and terminated.
o A ground conductor is properly installed.
o Battery cables are terminated on the positive and negative terminals in the UPS cabinet.
o Battery Shunt Trip and Battery Detect signal wiring is connected from the battery breaker to the UPS.
o Thermal Sensor signal wiring is connected from the battery cabinet to the UPS.
o All internal safety shields are installed.
o Air conditioning equipment is installed and operating correctly.
o The area around the UPS system is clean and dust-free.
o Adequate workspace exists around the IBC and other cabinets.
o Adequate lighting is provided around all IBC and UPS equipment.
o A 120 Vac service outlet is located within 7.5 meters (25 feet) of the IBC and UPS equipment.
o Startup and operational checks are performed by an authorized Eaton Customer Service Engineer.
o Visit
www.eaton.com/pq/register
to register your new Eaton UPS / Eaton UPS Accessory.
Eaton 93PM Integrated Battery Cabinet (IBC-L, IBC-LH [432V], and IBC-LH [480V]) Installation Manual 164000228—Rev 08
61

Advertisement

Table of Contents
loading

This manual is also suitable for:

Ibc-lh93pm ibc-l93pm ibc-lh

Table of Contents