Installing the junction box

1. Install the junction box 1.
2. Install the holder a on the wiring har-
ness to the junction box 1.
3. Fasten the wiring harness using the plas-
tic ties 2.
4. Install the ground lead terminal b and
junction box wiring harness extension
terminal c.
1
a
b
c
5. Install the PTT relay 3.
6. Connect the PTT relay coupler d.
7. Connect the PTT relay terminals e, and
then tighten the PTT relay terminal nuts
4 to the specified torque.
8. Install the caps 5.
7-33
Power unit
3
c
d
2
b
c
d
3
5
4
5
4
PTT relay terminal nut 4:
4 N·m (0.4 kgf·m, 3.0 ft·lb)

Installing the Rectifier Regulator

Do not reuse a gasket, always replace it
with a new one.
1. Install the anode 1 to the cover 2, and
then tighten the anode screw 3 to the
specified torque.
2. Install the gasket 4 and cover 2 to the
Rectifier Regulator, and then tighten the
Rectifier Regulator cover bolts 5 to the
specified torques in 2 stages.
1
3
4
Anode screw 3:
3 N·m (0.3 kgf·m, 2.2 ft·lb)
Rectifier Regulator cover bolt 5:
1st: 6 N·m (0.6 kgf·m, 4.4 ft·lb)
2nd: 12 N·m (1.2 kgf·m, 8.9 ft·lb)
3. Install the Rectifier Regulator 6, and
then tighten the Rectifier Regulator bolts
7 to the specified torques in 2 stages.
e