Commissioning
4.5 Basic Safety
● When you use the data set changeover CDS, you must delete the multiple assignment of
4.5.3.5
Further steps
● Commission the standard inverter functions by following the operating instructions. The
● Perform an acceptance test for the safety functions:
120
Figure 4-4
Remove pre-assignment of digital inputs DI 4 and DI 5
the digital inputs for all CDS.
link to the operating instructions can be found in the section Manuals for your inverter
(Page 229).
– Document your settings in an acceptance report.
– Check whether the safety functions are functioning correctly in your application.
– The instructions for the acceptance test can be found in the section Acceptance test -
Completion of commissioning (Page 164).
Safety Integrated Function Manual, SINAMICS G120 and G120C
Function Manual, 01/2011, FW 4.4, A5E03052391B AB