Commissioning and function test
ON
Power switch
(back of the
machine)
Appendix – Moving the ultimail to another location
• Fill water tank. Read Chapter 14.7 on
page 133.
• Switching on the ultimail metering sys-
tem: Switch the power switch on the
back of the postage meter to the
tion.
• Wait until the display shows the home
menu. The ultimail is ready for opera-
tion.
We recommend the following short
function test:
• Do a trial run. For instructions on the
trial run, read Chapter 4.3 on page 16.
• Adjust the ink cartridges if the meter
imprint has shifted position. Read
Chapter 14.3 on page 126.
• Clean the print system if necessary
(e.g. gaps in the print image). Read
Chapter 14.4 on page 127.
• Tare the scale. Read Chapter 13.12.1
on page 104.
171
I
posi-
Need help?
Do you have a question about the ultimail and is the answer not in the manual?
Questions and answers