Step 3 - Repeat for other rectifiers or fit blank panels
If not already fitted, fit rectifier blank panels in any vacant rectifier positions.
Procedure complete
Task 2 - Pre-Power-Up Checklist
Complete the checklist to confirm initial work is complete before progressing further.
All cabling is installed, securely tied and correctly insulated
Upstream surge protection is fitted (see Input Transient Protection on page 73)
Earth bonding is correct (see details on page 20)
DC battery and load cabling has the correct polarity
A registered electrician or other suitable approved person has checked the integrity of the
installed cabling
All panels are in place and all empty rectifier slots are covered with blanking panels
AC isolator and all AC MCBs are switched off
All DC Distribution MCBs are switched off and/or fuses removed
AC supply is isolated at each point of isolation leading back to the AC supply point
Batteries are electrically isolated from the DC power system
The site is clean
Copyright © 2005-2007 Eaton Corporation. All Rights Reserved.
IPN 997-00012-54A
July 2007
Start-Up
39
Need help?
Do you have a question about the Powerware 3G System SC200 and is the answer not in the manual?