Step 8 - Check terminations, secure cables and test insulation
Procedure complete
Installation Completed
Installation of the DV2-3G is now complete.
Now follow the instructions in Start-Up on page 38 to make the system operational.
Check all terminations are correct and are tightened.
1
Secure the cable with cable ties to ensure there is no strain on
2
terminals.
Test the insulation resistance of the conductors according to local AC
3
wiring regulations.
Replace all covers/panels.
4
Copyright © 2005-2007 Eaton Corporation. All Rights Reserved.
IPN 997-00012-54A
July 2007
Installation
35
Need help?
Do you have a question about the Powerware 3G System SC200 and is the answer not in the manual?