• Step 18:
Hold down the pneumatic control lever (2) of the ram (1).
The arm/cover assembly is lowered by the ram's jack into
the lowered position.
• Step 19:
Disconnect the quick release coupling from the air supply
(7.2) hose of the ram (1) control (2).
Connect it to the agitator air supply.
Adjust the air regulator (7.3) by controlling the rotation
speed of the agitator from the hatch.
Unscrew slightly the knob of the air regulator (7.3) - 6 bar
/ 87 psi maximum - to make the geared motor operate very
slowly for a few seconds, then bring it up to nominal speed.
IMPORTANT :
Do not operate the agitator outside the
drum or at too high speed.
It can lead to a deterioration of the paint, vibrations and an
early wear of the parts.
Do not run the equipment with no load.
• Step 20:
Close the hatch.
The agitation unit is ready to use.