3.9 START SEQUENCE

When the Control Box ON/OFF switch is set to the ON position, it checks all pre-purge safety
switches to ensure they are closed. These switches include:
Safety Shut-Off Valve Proof of Closure (POC) switch
Low Water Level switch
High Water Temperature switch
High Gas Pressure switch
Low Gas Pressure switch
The Blocked Inlet and downstream Blower Proof switches are not
checked prior to starting the pre-purge.
If all of the above switches are closed, the READY light above the ON/OFF switch will light and
the unit will be in the Standby mode.
When there is a demand for hot water, the following events will occur:
If any of the Pre-Purge safety device switches are open, the appropriate
fault message will be displayed. Also, if the required conditions are not
observed at any point during the start sequence, appropriate messages will
be displayed and the unit will go into fault mode.
OMM-0120_0A
GF-128-I
CHAPTER 3 – OPERATION
Available Choices or Limits
Minimum
-20
-20
Enabled or Disabled
0 Amps
0 Amps
NOTE
NOTE
AERCO International, Inc. • 100 Oritani Dr. • Blauvelt, NY 10913
Phone: 800-526-0288
- INTERNATIONAL
Maximum
+20
+20
Depends on unit type/size
2.5 Amps
2.5 Amps
Default
0
0
0.1 Amps
0.4 Amps
Page 45 of 174
11/15/2016

Advertisement

Table of Contents
loading

Table of Contents