2.4.2 Setting the Unit

The unit must be installed on a 4 to 6 inch (10.2 to 15.2 cm) housekeeping pad to ensure
proper condensate drainage. Two lifting lugs are provided with the unit and are wire-tied to the
top of the heat exchanger. The top sheet metal cover of the unit must first be removed and the
lifting lugs must be installed as shown in Figure 2-2. USE THESE TWO LUGS TO LIFT AND
MOVE THE UNIT. Remove the top panel from the unit to provide access to the lifting lugs.
Remove the four (4) lag screws securing the unit to the shipping skid. Lift the unit off the
shipping skid and position it on the 4 to 6 inch (10.2 to 15.2 cm) housekeeping concrete pad
(required) in the desired location.
In multiple unit installations, it is important to plan the position of each unit in advance. Sufficient
space for piping connections and future service/maintenance requirements must also be taken
into consideration. All piping must include ample provisions for expansion.
Figure 2-2. Partial Top View Showing Installed Lifting Lugs
If the Innovation Hot Water Boiler is equipped for use with the C-More
Water Heater Management (WHM) system, then an actuator-controlled ball
valve will be included with the shipment. Refer to section 2.5.1 for
installation instructions prior to connecting inlet piping.
OMM-0120_0A
GF-128-I
CHAPTER 2 – INSTALLATION
LIFTING LUGS
IMPORTANT
AERCO International, Inc. • 100 Oritani Dr. • Blauvelt, NY 10913
Phone: 800-526-0288
- INTERNATIONAL
Page 17 of 174
11/15/2016

Advertisement

Table of Contents
loading

Table of Contents