Foundations for multiple cabinets
The following figure shows the dimensions of the holes for anchoring the control cabinets
and the outer dimensions of four control cabinets installed side-by-side. You can arrange
more control cabinets. You wire the control cabinets to one another underground through
the foundation. You can find a schematic drawing and a table in section "Connecting charge
points to a multi-charging station (Page 95)".
Figure 5-12 Dimensions for multiple foundations
Screws for securing the charging station
To attach the charging station to the base area (Page 74), you need the following fasteners:
• 8 M12 screws
• 8 M12 washers
• 8 M12 cement sockets
5.5
Checking incoming goods
5.5.1
Checking the delivery for completeness and correctness
When the carrier delivers the charging station, immediately perform an incoming goods
inspection.
Checking delivery
Start the incoming goods inspection with the following steps:
• Check the delivery for completeness.
• Check that the shipping documents match the items delivered.