Commissioning
5.4 Quick commissioning with a PC
5.4.3

Go online and start the configuration wizards

Procedure with STARTER
Proceed as follows to start the quick commissioning of the inverter:
1. Select your project and go online:
2. In the following screen form, select the inverter with
which you wish to go online.
3. Download the hardware configuration found online in
your project (PG or PC).
Significance of the symbol in front of the inverter:
(A) The inverter is online.
(B) The inverter is offline
4. When you are online, double-click on "Control Unit".
5. Start the commissioning wizard:
You have started the quick commissioning of the inverter.
Procedure with Startdrive
Proceed as follows to start the quick commissioning of the inverter:
1. Select your project and go online:
2. In the following screen form, select the inverter with which you wish to go online.
3. Once you are online, select "Commissioning" → "Commissioning Wizard":
You have started the quick commissioning of the inverter.
94
.
Operating Instructions, 07/2016, FW V4.7 SP6, A5E34262100B AD
Converter with control units CU240D-2

Advertisement

Table of Contents
loading

This manual is also suitable for:

Cu240d-2

Table of Contents