4.4
Removing server nodes from the server
enclosure
The server enclosure must always run with closed node bays. It is only
allowed to leave a bay open for a limited time in case of repairing a
server node (for example). In the meantime all remaining server nodes
run in throttling mode (with reduced performance).
Removing the CX2550 M6 or CX2560 M6 server node
CAUTION
Follow the safety instructions in
▶ Shut down the server node and disconnect all external cables.
Figure 3: Removing the CX2550 M6 or CX2560 M6 server node (A)
▶ Unlock the lever tip (1).
CX400 M6
Upgrade and Maintenance Manual
Basic hardware procedures
"Important information" on page
25.