Commissioning the Unit

Perform the following steps for commissioning the unit with the Siemens LMV3:
NOTE:
A combustion analyzer will be needed when performing changes to the
profile. Combustion settings should only be adjusted by a qualified factory trained
and certified technician.
1. Press and hold the "F" and "A" buttons simultaneously. You will be
prompted for your password (####).
NOTE:
Note: #### is the last four digits of the national board number.
2. Enter your password and press the "Enter" button.
3. Using the "+" or "–" button, scroll to parameter level 400. Press the "Enter"
button. RUN will appear. Press the enter button again.
4. Turn the boiler on and make sure that there is a call for heat. PH12 means
the unit is in standby and is looking for a call for heat to start. The unit
should start to Pre-purge (PH22) and drive to 100% purge (PH24), then
begin purge countdown in PH30.
5. Once the control has reached the Ignition Position (PH36), press the "+"
button. This will allow the boiler to ignite the pilot flame. Once the pilot is
established, the boiler will transfer to main flame.
6. You will be at P0. P0 is the start of the profile and the Ignition position.
7. Make changes to the fuel profile. Three changes will need to be made: fan
output, fuel and air settings. To make changes:
» Safely drive the unit to the high-fire position, P9, by pressing the "+"
button to proceed from P0 through P9.
» Check the O2 level in the stack outlet.
» Once the desired O2 level and input (last elbow pressure) is reached,
proceed to the next combustion point until all points have been set.
8. Back out to the front screen by pressing the "–" and "+" buttons together.
ƒ Adjusting the Profile
See the table, below, for a Siemens LMV3 fault history listing. Refer to Table
8 at the end of this section of this manual for Siemens LMV3 parameter
information.
Questions? Please Contact Your Local Manufacturer's Representative
OPERATION
!
WARNING
This information is for reference purposes
only. Fulton Companies is not responsible
for this product, including (but not limited
to) its accuracy, reliability, and safety. No
Fulton document should substitute for full
review of documentation available from
the product manufacturer.
3-7

Advertisement

Table of Contents
loading

Table of Contents