Function test during commissioning

An error must be simulated for each safety-related output during commissioning: The anti-
cipated error reaction must occur when an output has a short circuit to a supply voltage.
Operating Manual PSSu K F FAU B, PSSu K F FAU P
1003434-EN-05
INFORMATION
The short circuit test must be performed on the load and not on the output
terminal.