Configure an E1/T1 card
2. If the DDCH is disabled, enter the command in LD 96 to enable the DDCH:
3. To enable the D-channels, enter the command in LD 96:
4. To request the current status of the D-channel, enter the command:
Enabling the NTAK93AB daughterboard
1. In LD 75, enter the command to enable all PRI loops:
2. Enter the command to enable the DCHI where the DCHI is enabled, but all channels
3. To enable the D-Channels, enter this command:
4. To request the current status of the D-channel, enter the command:
Enabling the clock controller
1. In LD 60, enter the command to enable the system clock controller on the specific
2. Enter the command to enable clock tracking on the Gateway specified by the
3. To check the status of the system clock on the specified superloop and shelf, enter
102
Media Gateway 1000E PRI Gateway Installation and Commissioning
ENLL L
ENL MSDL sl s c
ENL DCH X
STAT DCH
If the D-channel is established and operational, the system responds with DCH x
EST in LD 96.
ENL DDCS 1
are disabled:
ENL DDSL n
STRT n
STAT DDSL
If the D-channel is operational and enabled, the response is ENBL ACTIVE . All
configured channels are normally enabled.
superloop and shelf:
ENI CC 1 s
superloop and shelf tracking to primary, secondary, or free run:
TRCK aaa 1 s
where aaa is:
• PCK for the primary track clock
• SCLK is the track secondary clock
• FRUN is the free run mode
the command: