Preparation Checklists
Data Center Room Considerations
Are there any ramps, stairs, or thresholds that are in the
moving path for the new hardware?
Have you confirmed that the access route is free of any
obstacles that would expose the device to shock?
If there are stairs, then is a loading elevator accessible
for moving the equipment?
Has the rack location been allocated?
Is there a vacant space in the rack for the new server?
Does the floor layout meet the equipment maintenance
access requirements?
Is there adequate space available for server
maintenance?
Have cabinet stabilization measures been considered?
Will the hardware location require any non-standard
cable lengths?
Is the floor to ceiling height a minimum of 2914 mm or
2.9 m (9.6 feet)?
Is the depth of the raised floor a minimum of 460 mm
(18 inches)?
Related Information
"Rack Requirements" on page 38

Data Center Environment Checklist

Complete the following checklist to ensure that the data center environment requirements are
met for the server.
TABLE 11
Data Center Environment Considerations
Does the computer room air handling meet temperature
and humidity requirements?
Does the installation floor layout satisfy the ventilation
requirements?
Will the equipment be positioned so that the exhaust
air of one rack does not enter the air intake of another
rack?
134
Oracle Server X6-2 Installation Guide • July 2020

Data Center Environment Checklist

Yes
No
N/A
Comment
Yes
No
N/A
Comment

Advertisement

Table of Contents
loading
Need help?

Need help?

Do you have a question about the Server X6-2 and is the answer not in the manual?

Questions and answers

This manual is also suitable for:

X6-2l

Table of Contents