3.3

Check lists when commissioning SINAMICS S

Checklist for commissioning booksize power units
The following checklist must be carefully observed. Read the safety instructions in the
manuals before starting any work.
Table 3- 1
Check
Are the environmental conditions in the permissible range?
Is the component firmly attached to the fixing points provided?
Is the specified air flow for cooling the devices ensured?
Have the ventilation clearances for the components been observed?
Is the memory card correctly inserted in the Control Unit?
Are all necessary components of the configured drive line-up available, installed and
connected?
Do the temperature monitoring circuits fulfill the specifications of protective separa-
tion?
Have the DRIVE-CLiQ topology rules been observed?
Have the line-side and motor-side power cables been dimensioned and routed in
accordance with the environmental and routing conditions?
Have the maximum permitted cable lengths between the frequency converter and the
motor (depending on the type of cables used) been observed?
Have the power cables been properly connected to the component terminals with the
specified torque?
Have all of the remaining screws been tightened to the specified torque?
Has all wiring work been successfully completed?
Are all connectors correctly plugged in and screwed in place?
Have all the covers for the DC link been closed and latched into place?
Have the shield supports been correctly connected through a large surface area?
Commissioning with Startdrive
Commissioning Manual, (IH3), 07/2016, 6SL3097-4AA10-0BP0
Checklist for commissioning (booksize)
3.3 Check lists when commissioning SINAMICS S