5: Conduct An Indicator Test; 6: Conduct A Walk Test; 7: Conduct A Communicator Test; 8: Manual Alarmnet Registration - Honeywell Farenhyt Series Installation And Operation Manual

Addressable fire alarm control system emergency communication system
Hide thumbs Also See for Farenhyt Series:
Table of Contents

Advertisement

4.
Press any key to end the drill. (If you do not press any key to end the fire drill manually, it will time out automatically after ten
minutes).
If a fire drill switch has been installed, activating the switch will begin the drill; deactivating the switch will end the drill.
10.4.5 Conduct an Indicator Test
The indicator test checks the annunciator LEDs, PZT, and LCD display.
1.
From the Main Menu, press 1 for System Tests.
2.
Press 2 for Indicator Test. The system turns on each LED several times, beeping the PZT as it does so. At the same time it scrolls
each available character across the LCD. A problem is indicated if any of the following occurs:
An LED does not turn on;
You do not hear a beep;
All four lines of the LCD are not full.
This test takes approximately 15 seconds to complete. You can press any key to end manually while the test is still in progress. When the
test ends, you will be returned to the <Test Menu>.
10.4.6 Conduct a Walk Test
Walk Test is a feature which allows one person to test the fire alarm system. The Walk Test will run for 4 hours or until the user manually
exits. If an alarm or pre-alarm condition is occurring in the system, you will not be able to enter the walk test. A walk test may only be
initiated if the test is enabled in the user profile.
1.
From the Main Menu, press 1 for System Tests.
If any alarm verification zones are being used, the user will be asked if they wish to disable alarm verification during
walk test. This occurs for either walk test option.
2.
Select 3 for Walk Test-No Rpt. Enter the time period you wish the NAC circuit to be active for each alarm (06 to 180 seconds). The
LCD will display "WALK TEST STOPPED" on Line 1 and "ENTER = start test" on Line 3. By selecting this option, central station
reporting is disabled while the test is in progress.
Select 4 for Walk Test-with Rpt. Enter the time period you wish the NAC circuit to be active for each alarm (06 to 180 seconds).
The LCD will display "WALK TEST STOPPED" on Line 1 and "ENTER = start test" on Line 3. By selecting this option, central
station reporting will occur as normal during the walk test.
The panel generates a TEST report to the central station when the walk test begins. During a walk test, the panel's normal fire alarm
function is completely disabled, placing the panel in a local trouble condition. All zones respond as 1-Count zones (respond when a
single detector is in alarm) during a walk test. Each alarm initiated during the walk test will be reported and stored in the event
history buffer.
3.
To End the Walk test, go to the main menu. Select 1 for System Test, then press 3 or 4. Press ENTER to end the walk test. The
system will reset. The panel will send a "TEST RESTORE" report to the central station.
If you do not end the walk test manually within four hours, it will end automatically. If an alarm or pre-alarm condition is occurring in
the system, you will not be able to enter the walk test.
NOTE: The panel does not do a full 30 second reset on resettable power outputs. As soon as the device is back to normal, the panel is ready
to go to the next device.
10.4.7 Conduct a Communicator Test
1.
From the Main Menu, press 1 for System Tests.
2.
Select 5 for Communicator Test. The screen will display "Manual communicator test started". When the test is completed, you will
be returned to the <Test Menu>. A manual communicator test requires that at least one daily test in the network be enabled in
communicator programming.
3.
The Manual communicator test will be communicated out both Phone Lines and Ethernet/Cellular paths if they are all programmed.
Each manual communicator test will alternate between one of the Phone Line paths and one of the AlarmNet paths.
10.4.8 Manual AlarmNet Registration
1.
From the Main Menu, press 1 for System Tests.
2.
Select 8 for Register AlarmNet. The screen will display and ask for confirmation. Feedback will be given if the command was sent
or not.
IFP-300 / IFP-300ECS Manual P/N LS10145-001SK-E:B 12/18/2017
IMPORTANT!
136

Advertisement

Table of Contents
loading

This manual is also suitable for:

Farenhyt ifp-300Farenhyt ifp-300ecs

Table of Contents