Removing the control panel from the 9040-MR9
To remove a control panel, complete the steps in this procedure.
1. Ensure that you have the electrostatic discharge (ESD) wrist strap on and that the ESD clip is plugged
into a ground jack or connected to an unpainted metal surface. If not, do so now.
2. Access the Advanced System Management Interface (ASMI).
Attention: During this procedure: Do not reset the service processor, do not remove the service
processor card, and do not power off and power on the system.
3. In the navigation area, select Concurrent maintenance > Control Panel.
4. In the Control Panel window, select the Remove action and press Continue.
5. Verify that the location code D1 for the control panel is selected and then click Save Settings.
6. If the operation was successful, the window displays Operation completed successfully. You can
then remove the control panel.
7. Lift up the retaining clip (A) under the control panel and remove the control panel from the front of the
system as shown in the following figure.
Figure 3: Removing the control panel
Control panel and control panel display for the 9040-MR9 3

Hide quick links:

Advertisement

Table of Contents
loading
Need help?

Need help?

Do you have a question about the Power System Series and is the answer not in the manual?

This manual is also suitable for:

Power system e950 9040-mr9

Table of Contents

Save PDF