Preparing the system for operation after removing and replacing the control panel display
in the 9040-MR9
To prepare the system for operation after removing and replacing a control panel display, complete the
steps in this procedure.
1. Ensure that you have the electrostatic discharge (ESD) wrist strap on and that the ESD clip is plugged
into a ground jack or connected to an unpainted metal surface. If not, do so now.
2. Position the cover (A) on the front of the system unit as shown in the following figure, so that the four
pins (B) on the system match the four holes at the rear of the cover.
Press the tabs (C) to snap the cover into position.
Figure 10: Installing the front cover
3. Turn off the identify LED. For instructions, see Deactivating an identify LED (www.ibm.com/support/
knowledgecenter/POWER9/p9haj/p9haj_turn_off_identify_led.htm).
10 Power Systems: Temple's Zeppelin procedures for install, remove, replace

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

Power system e950 9040-mr9

Table of Contents