Operating And Display Panel; Mounting; Connection - Bosch ICP-MAP5000-2 Installation Manual

Hide thumbs Also See for ICP-MAP5000-2:
Table of Contents

Advertisement

MAP5000
3.
4.
5.
6.
7.
3.10

Operating and Display Panel

In the case of VdS systems, at least one control center (IUI-MAP0001) or an operating and
display panel must be provided for each independent area.
3.10.1

Mounting

It must ensured by organizational measures that the operating and display panel is not
generally accessible. An ISP-EMIL 120 Expansion Module is required for activation of the
operating and display panel. The cable length between the expansion module and operating
panel must not be longer than 3 m. Installation must take place at viewing height, i.e. approx.
150 to 160 cm above the floor.
3.10.2

Connection

Make the LSN connections of the ISP-EMIL 120 Expansion Module in accordance with the
installation instructions of the expansion module. Wiring of the operating and display panel
with the ISP-EMIL 120 Expansion Module must take place as follows:
Bosch Sicherheitssysteme GmbH
Refer to Figure 3.4 Data Bus Connection of the Control Center on the External BDB, page 41
for wiring instructions.
Replace the control center cover on the base.
The cover automatically locks to the base.
Secure the cover using the two screws M3 x 20 mm. (F.01U.172.636).
The fed-in cable must be provided with strain relief.
The adhesive seal must be attached after completion of all work.
Installation Manual
Cable Connections | en
53
2014.12 | 13 | F.01U.168.332

Advertisement

Table of Contents
loading

This manual is also suitable for:

Map5000 seriesIcp-map5000-com

Table of Contents