4 4 . . 7 7 . . 5 5 I I n n s s t t a a l l l l i i n n g g E E x x t t e e r r n n a a l l P P a a r r a a l l l l e e l l C C A A N N C C o o n n t t r r o o l l W W i i r r i i n n g g a a n n d d C C o o n n n n e e c c t t i i o o n n s s
NOTE 1
If installing interface wiring connections between standalone cabinets, conduit must be
installed between each cabinet.
NOTE 2
Disconnect terminal block plugs from terminal blocks to wire plugs.
To install wiring:
1.
Verify the UPS system is turned off and all power sources are removed. See
Chapter 7 UPS Operating Instructions
2.
If not already opened, open the front door by lifting the latch from the bottom and turning to the right
(counterclockwise) and swing the door open.
3.
If wiring the external parallel CAN connections using the inter-cabinet wiring access pass-through (line-up-
and-match configurations), proceed to Step 4; if wiring the external parallel CAN connections using bottom
entry access, proceed to Step 6; if wiring the external parallel CAN connections using top entry access,
proceed to Step 12.
4.
Pass-through Wiring. Route the external parallel CAN control wiring between UPS cabinets through the
top UPS inter-cabinet wiring access pass-through to the UPS external parallel terminals. See
UPS wiring access information, and
5.
Proceed to Step 15.
6.
Bottom Entry Wiring. Remove the bottom interface entry conduit landing plate to drill or punch holes
(see
Figure
24).
7.
Reinstall the interface entry plate and install the conduit.
8.
Route the external parallel CAN control wiring through the bottom interface entry conduit landing plate to
the bottom access interface wiring channel along the inside of the front door.
9.
Route the wiring along the interface wiring channel to the UPS external parallel terminals.
10. Secure the wiring to the wire tie anchors provided (see
11. Proceed to Step 15.
12. Top Entry Wiring. Remove the top interface entry conduit landing plate to drill or punch holes (see
Figure
17).
13. Reinstall the interface entry plate and install the conduit.
14. Route the external parallel CAN control wiring through the top interface entry conduit landing plate to the
UPS external parallel terminals.
15. Connect the external parallel CAN wiring to the CAN terminals. See paragraph
3.2.4 UPS System Interface Wiring
requirements, and
Figure 31
16. If wiring external parallel pull chain connections, proceed to paragraph
4.7.6 Installing External Parallel Pull Chain Control Wiring and
proceed to paragraph
4.7.7 Installing Minislot Interface
to paragraph
4.8 Installing a REPO
17. Close the UPS outside door and secure the latch.
Eaton 93PM UPS (400V/480V Four-Wire – 100 kW Frame) Installation and Operation Manual 164000566—Rev 04
for shutdown instructions.
Figure 22
and
Figure 23
Figure
Preparation,
Table
27, and
and
Figure 32
for wiring information and terminal assignments.
Connections; if wiring REPO connections, proceed
Switch; otherwise, proceed to Step 17.
UPS System Installation
for UPS interface terminal locations.
25) using Zip ties.
Table 28
for wiring and termination
Connections; if wiring Minislot connections,