Eaton 93PM Installation And Operation Manual page 123

400v/480v four-wire 100 kw frame
Table of Contents

Advertisement

8.
If requested, enter the Level 1 password. Default password is 1111.
The rectifier and inverter turn on. The inverter continues to ramp up to full voltage.
Once the inverter reaches full voltage, the UPS inverter switchgear closes and the static switch turns off.
Power is now supplied to the critical load in dual conversion mode. It takes approximately one minute for
the UPS to achieve the dual conversion mode.
The Normal status indicator is illuminated.
7 7 . . 3 3 . . 2 2 S S t t a a r r t t i i n n g g t t h h e e U U P P S S i i n n B B y y p p a a s s s s M M o o d d e e
If the inverter output of the UPS is not available and the critical load needs to be energized:
In Bypass mode, the critical load is not protected from commercial power interruptions and abnormalities.
1.
Close the UPS input feeder circuit breaker.
2.
If dual feed, close the UPS bypass feeder circuit breaker.
3.
If IBCs are installed, close the battery breakers.
4.
Observe the UPS control panel display becoming active, indicating logic power.
5.
Verify no alarms are active.
6.
Tap the CONTROLS tab on the main menu navigation bar. The System Control screen is displayed.
7.
Tap the GO TO BYPASS button.
The critical load is immediately supplied by the bypass source, in Bypass mode.
The BYPASS status indicator is illuminated.
7 7 . . 3 3 . . 3 3 S S t t a a r r t t i i n n g g t t h h e e U U P P M M s s
To start the power modules without transferring the critical load to Double Conversion mode:
1.
Close the UPS input feeder circuit breaker.
2.
If dual feed, close the UPS Bypass input feeder circuit breaker.
3.
Observe the UPS control panel becoming active, indicating logic power.
4.
Verify no alarms are active.
5.
Tap the CONTROLS tab on the main menu navigation bar. The System Control screen is displayed.
6.
Tap the MODULES CONTROLS tab on the secondary Control menu navigation bar. The UPM Select
screen is displayed.
7.
On the UPM Select screen, select UPM 1. The UPM Control Screen is displayed.
8.
Tap the START MODULE button.
The UPM 1 rectifier and inverter turn on. When the inverter reaches full voltage, the UPS is ready to
transfer to the Double Conversion mode and supply the critical load.
9.
Repeat Steps
Step 5
through
The UPM 2 rectifier and inverter turn on. When the inverter reaches full voltage, the UPS is ready to
transfer to the Double Conversion mode and supply the critical load.
10. Repeat Steps
Step 5
through
Eaton 93PM UPS (400V/480V Four-Wire – 100 kW Frame) Installation and Operation Manual 164000566—Rev 04
CAUTION
Step 8
selecting UPM 2 to start UPM 2.
Step 8
selecting UPM 3 to start UPM 3.
UPS Operating Instructions
113