UPS System Installation
14. If a sidecar is attached to the UPS, remove the sidecar mounting bolts holding the front and rear sidecar
supports to the cabinet base.
15. Remove the cabinet mounting bolts holding the front and rear supports to the cabinet base.
16. If installing the cabinet permanently, retain the cabinet mounting bolts; otherwise, recycle the bolts along
with the support brackets in a responsible manner.
17. Close the door and secure the latch.
18. If a sidecar is attached to the UPS, remove the screws securing sidecar rear shipping bracket. Remove the
bracket and reinstall the screws (see
19. If the leveling feet are not retracted, turn all four leveling feet until they are retracted as far into the cabinet
as possible.
To prevent tipping when rolling the cabinet, push the cabinet from the rear whenever possible.
20. Roll the cabinet to the final installation location.
21. Lower the UPS's leveling feet and using a bubble level, adjust the leveling feet accordingly until the cabinet
is level.
22. If installing the IBC adjacent to the UPS, locate the top splice bracket shipped with the IBC; otherwise go
to Step 25.
23. Remove the screws along each adjacent cabinet top panel securing the top panels. Retain the hardware
for later use.
24. Install the top splice bracket between the adjacent cabinet and secure the tie strap with retained hardware.
NOTE
25. If permanently mounting the UPS using the left and right side floor mounting brackets, proceed to
Step 26; if using the front and rear floor mounting brackets, proceed to Step 30; otherwise, proceed to
Step 33.
26. Locate the left and right side floor mounting brackets from the floor mounting kit.
27. Using the retained cabinet mounting bolts, install the floor mounting brackets to the left and right side of
the UPS with the angle facing outward.
28. Secure the cabinet to the floor with customer-supplied hardware.
29. Proceed to paragraph
30. Locate the front and back floor mounting brackets from the floor mounting kit.
31. Using the retained cabinet mounting bolts, install the floor mounting brackets to the front and rear of the
UPS with the angle facing outward.
32. Secure the cabinet to the floor with customer-supplied hardware.
NOTE
33. Locate the black cover dots from the parts kit and install over the left and right side bracket mounting
holes.
34. Proceed to paragraph
56
Eaton 93PM UPS (400V/480V Four-Wire – 100 kW Frame) Installation and Operation Manual 164000566—Rev 04
Figure
Either front and back floor mounting brackets or left and right side floor mounting
brackets are available for permanently mounting the UPS.
4.3 Integrated Battery Cabinet
Black cover dots are provided, if side mounting bracket holes need to be covered for
aesthetic reasons.
4.3 Integrated Battery Cabinet
16).
CAUTION
Installation.
Installation.

Advertisement

Table of Contents
loading

This manual is also suitable for:

93pm series93pm-50-293pm-50-1

Table of Contents