Danfoss VACON 100 INDUSTRIAL Operating Manual page 45

Wall-mounted drives
Hide thumbs Also See for VACON 100 INDUSTRIAL:
Table of Contents

Advertisement

Operating Guide | VACON® 100 Wall-mounted Drives
Procedure
1. Strip the motor cable, the mains cable, and the brake resistor cable. See
®
The VACON
100 FLOW and HVAC software do not have the dynamic braking or the brake resistor functions.
2. Put the grommets in the openings of the cable entry plate. These parts are included in the package.
3. Put the cables in the openings of the cable entry plate.
4. Cut the grommets open to move the cables through them.
A Do not cut the grommet openings wider than what is necessary for the used cables.
B If the grommets fold in when putting the cable, pull the cable back to make the grommets straight.
A
A The mains cable
C The motor cable
Illustration 12:
5. With the protection rating IP54, the connection between the grommet and the cable must be tight. Pull the first bit of the cable out
of the grommet so that is stays straight. If this is not possible, make the connection tight with some insulation tape or a cable tie.
6. Remove the grounding clamps for cable shield and the grounding clamps for grounding conductor. The tightening torque is 2.2
Nm or 19.5 lb-in.
Danfoss A/S © 2019.05
B
C
Installing Cables through Grommets
10.4 Cable Stripping
Lengths.
B The brake cable
AQ298036140958en-000101 / DPD01711| 45
Electrical Installation

Advertisement

Table of Contents
loading

This manual is also suitable for:

Vacon 100 hvacVacon 100 flow

Table of Contents