2.1.8. Initial Commissioning
The easiest way of carrying out the initial commissioning is by using the Quick Menu button and follow the quick set-up procedure using LCP 102 (read
table from left to right):
2
Press
0-01 Language
1-20 Motor power
1-22 Motor voltage
1-23 Motor frequency
1-24 Motor current
1-25 Motor nominal speed
5-12 Terminal 27 Digital Input
1-29 Automatic Motor Adaptation
3-02 Minimum reference
3-03 Maximum reference
3-41 Ramp1 up time
3-42 Ramp1 down time
3-13 Reference site
18
Q2 Quick Menu
Set language
Set Motor nameplate power
Set Nameplate voltage
Set Nameplate frequency
Set Nameplate current
Set Nameplate speed in RPM
Coast inverse
If terminal default is
No function
setting to
. No connection to terminal 27 is then
needed for running AMA
Set desired AMA function. Enable complete AMA is recommen-
ded
Set the minimum speed of the motor shaft
Set the maximum speed of the motor shaft
Set the ramping up time with reference to nominal motor speed
(set in par. 1-25)
Set the ramping down time with reference to nominal motor
speed (set in par. 1-25)
Set the site from where the reference must work
®
MG.33.M3.02 - VLT
is a registered Danfoss trademark
FC 300 Programming Guide
it is possible to change this

Advertisement

Table of Contents
loading
Need help?

Need help?

Do you have a question about the FC 300 and is the answer not in the manual?

Table of Contents