Step 4: Verifying Proper Power Optimizer Connection - SolarEdge StorEdge SE5000-xxS0 series Installation Manual

For single battery or high capacity
Table of Contents

Advertisement

Chapter 2: Installing the Power Optimizers
Step 4: Verifying Proper Power Optimizer
Connection
After a module is connected to a power optimizer, the power optimizer outputs a safe voltage of 1V. 
Therefore, the total string voltage should be equal to 1V times the number of power optimizers 
connected in series in the string. For example, if 10 power optimizers are connected in a string, then 10V 
should be produced.
Make sure the modules are exposed to sunlight during this process; otherwise, the power optimizers may 
not be powered. If you use a tracker, the power optimizer will turn ON only if the tracker is tracking the 
sun and the module provides at least 2W.
In SolarEdge systems, due to the introduction of power optimizers between the PV modules and the 
inverter, the short circuit current I
 and the open circuit voltage V
 hold different meanings from 
SC
OC
those in traditional systems. 
For more information about the SolarEdge   s ystem's string voltage and current, refer to 
the V
 and I
 in SolarEdge Systems Technical Note, available on the SolarEdge website at: 
OC
SC
http://www.solaredge.com/files/pdfs/isc_and_voc_in_solaredge_systems_technical_
note.pdf . 
To verify proper power optimizers connection:
Measure the voltage of each string individually before connecting it to the other strings or to the inverter. 
Verify correct polarity by measuring the string polarity with a voltmeter. Use a voltmeter with at least 
0.1V measurement accuracy.
For troubleshooting power optimizer operation problems, refer to Power Optimizer Troubleshooting  on 
page 85.
15
SolarEdge-StorEdge -Single Battery/High Capacity Installation MAN-01-00283-1.1