Commissioning

Before you can start commissioning the safety functions, you must carry out the following
steps (providing these are necessary for your application):
● Create the higher-level control program, e.g. SIMATIC.
● Wire and configure the inverter inputs and outputs.
● Establish a connection to the fieldbus.
An overview of all the commissioning steps can be found in the section Commissioning
guidelines (Page 12)
4.1

Commissioning: Offline or online

You can parameterize the safety functions both offline and online. We strongly recommend
that you commission the safety functions with the STARTER PC tool.
This manual provides a detailed description of the online commissioning procedure. The
section Offline commissioning (Page 113) describes the important points to remember when
commissioning the safety functions offline.
The operating instructions describe how to go online with STARTER.
Safety Integrated Function Manual, SINAMICS G120
Function Manual, 07/2010, FW 4.3.2, A5E03052391B AA
– The "standard" inputs and outputs are described in the operating instructions
(Overview of documentation (Page 10)).
– The fail-safe inputs are described in this manual in the section Activation via F-DI
(Page 43).
– The procedure for establishing a connection to "standard" communication is described
in the operating instructions.
– The PROFIsafe connection is described in this manual in the section Activation via
PROFIsafe (Page 60).
4
69