Chapter 3
Cisco RFGW-10 UEQAM Installation

Steps

Caution
Do not connect the AC power cables to the facility power sources until the DC power cables are
connected to the power shelf, and to the Cisco RFGW-10 UEQAM.
To connect a single power shelf to the DC PEM modules on the Cisco RFGW-10:
Step 1
Connect the Y-Shaped DC power cables to the Lineage power shelf, see the
section on page
Step 2
Connect the DC power cables to the DC-input terminals on the Cisco RFGW-10 UEQAM. For
information on connecting the DC power cables to the Cisco RFGW-10, see the
Power to Cisco RFGW-10 UEQAM" section on page 3-22.
Step 3
Connect the AC power cables to a standard wall socket (facility power source) to provide power to the
Cisco RFGW-10. See the
Figure 3-22
Figure 3-22
3
OL-16264-04
3-29.
"Powering On the Cisco RFGW-10 UEQAM" section on page
shows the Lineage power shelf connected to the DC PEM modules.
Lineage Power Shelf Connected to DC PEM Modules - Configuration 1
2
5
Connecting the Lineage Power Shelf to the Cisco RFGW-10
1
6
5
4
Cisco RF Gateway 10 Hardware Installation Guide
"Cabling the Power Shelf"
"Connecting DC-Input
3-28.
2
3
3-31