Chapter 6 - Current Protection Functions
3.4

APPLICATION NOTES

3.4.1

PARALLEL FEEDERS

Figure 36: Typical distribution system using parallel transformers

In the application shown in the diagram, a fault at 'F' could result in the operation of both R3 and R4 resulting in
the loss of supply to the 11 kV busbar. Hence, with this system configuration, it is necessary to apply directional
protection devices at these locations set to 'look into' their respective transformers. These devices should co-
ordinate with the non-directional devices, R1 and R2, to ensure discriminative operation during such fault
conditions.
In such an application, R3 and R4 may commonly require non-directional overcurrent protection elements to
provide protection to the 11 kV busbar, in addition to providing a back-up function to the overcurrent devices on
the outgoing feeders (R5).
For this application, stage 1 of the R3 and R4 overcurrent protection would be set to non-directional and time
graded with R5, using an appropriate time delay characteristic. Stage 2 could then be set to directional (looking
back into the transformer) and also have a characteristic which provides correct co-ordination with R1 and R2.
Directionality for each of the applicable overcurrent stages can be set in the directionality cells (I>1 Direction).
Note:
The principles outlined for the parallel transformer application are equally applicable for plain feeders that are operating in
parallel.
102
R1
OC/EF
SBEF
R3
DOC/DEF
OC/EF
R5
OC/EF
E00603
33 kV
R2
OC/EF
R4
DOC/DEF
OC/EF
11 kV
Loads
P14x
P14xEd1-TM-EN-1

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents