IMPLEMENTATION

Electrical InterMiCOM is configured using a combination of settings in the INTERMICOM COMMS column, settings in
the INTERMICOM CONF column, and the programmable scheme logic (PSL).
The eight command signals are mapped to DDB signals within the product using the PSL.
Signals being sent to a remote terminal are referenced in the PSL as InterMiCOM out 1 - InterMiCOM out 8. Signals
received from the remote terminal are referenced as InterMiCOM in 1 - InterMiCOM in 8.
374
P14xEd1-TM-EN-1