8. Remove the communication cables from interface X2 (port 1 and port 2).
9. Remove the ground connection by releasing the grounding screw.
10. To remove the I/O module, release the fixing screws.
11. Note down the address set with DIP switch S1 on the defective module.
4.5.6

This is how you install the PP 72/48D 2/2A PN

Installing
Procedure:
1. Set DIP switch S1 of the new module as you previously noted down.
2. Install the new I/O module.
3. Connect the ground connection.
4. Connect the communication cables at interface X2 (port 1 and port 2).
5. Re-establish the strain relief for the communication cables.
6. Re-insert the connectors of the ribbon cables (X111, X222, X333) on the module that are
7. Reconnect power supply X1.
8. Close the cabinet and switch-on the system again.
DIP switch S1
Setting of switch S1:
1
2
3
4
on
off
off
on
off
off
off
on
on
on
on
off
off
on
on
off
on
off
on
off
The switch positions 9 and 10 guarantee the PROFINET functionality of the module and must always be switched "on".
NOTICE
A new address only becomes effective after voltage OFF → ON.
Hardware and Software
Service Manual, 03/2011, 6FC5397-5DP40-0BA0
used to connect the digital inputs and outputs.
5
6
7
off
off
off
off
off
off
off
off
off
off
off
off
off
off
off
8
9
10
Device name
on
on
off
pp72x48pn9
off
pp72x48pn8
off
pp72x48pn7
off
pp72x48pn6
off
pp72x48pn5
Service cases - hardware
4.5 I/O modules
109

Advertisement

Table of Contents
loading

Table of Contents