Planning

Preparing and planning for the upgrade
Planning for an upgrade involves the following tasks:
Read and understand the current release Product Bulletin.
Review the current release product bulletin related specifically to the
software being upgraded.
Conduct a site inspection to determine proper power and grounding.
Review the site profile to determine proper foot space if adding new
columns or modules.
Note: For information about adding new network shelves, see
Communication Server 1000M and Meridian 1 Large System Installation
and Commissioning (NN43021-310).
Ensure sufficient power for new columns/modules or applications.
Identify all applications that are currently installed on the source
platform.
Identify and correct outstanding service problems.
Verify the site log is updated with current trunking, call routing,
application notes, and site contact information.
Review all product bulletins and Avaya Alerts that impact the site.
Determine if software can be converted on site or must be sent to Avaya.
Prepare a contingency plan for backing out of the upgrade.
DANGER OF ELECTRIC SHOCK
In a DC-powered system, power to the column can
remain on during the following procedures. In an
AC-powered system, however, power to the entire
column must be shut down throughout the procedures.
CS 1000M SG CP PIV to CS 1000M MG CP PIV FNF Upgrade
Page 20 of 159

Advertisement

Table of Contents
loading

This manual is also suitable for:

1000m seriesCs 1000m sgCs 1000m mg

Table of Contents