Commissioning
9.4 Differential pressure and flow rate
Procedure
To commission the transmitter for gases, proceed as follows:
1. Open both the shut-off valves
2. Open the stabilizing valve
3. Open the differential pressure valve (
4. Check and if required correct the zero point when the start of scale value is 0 mbar
(4 mA).
5. Close the stabilizing valve
6. Open the other differential pressure valve (
9.4.3

Commissioning for liquids

Usual arrangement
,
Transmitter below the differential pressure
transducer
160
Pressure transmitter
Stabilizing valve
Differential pressure valves
Differential pressure lines
Shut-off valves
at the pressure tapping point.
.
or
).
.
or
Special arrangement
Drain valves
Gas collector vessels (optional)
Differential pressure transducer
Vent valves
Transmitter above the
differential pressure transducer
).