Commissioning report

z Sign all commissioning work as completed and enter
the relevant date.
Commissioning steps
1.
Carry out pressure test on items delivered separately.
2.
Filling the heating system
3.
Check heating system for leaks
- enter fill water amount and quality in operator's log
(included with the technical documentation).
4.
Check the position of the hot gas baffles (the 16-section
boiler has no hot gas baffles)
5.
Start up the control panel
6.
Check the flue pipe for leaks.
7.
Commission the burner
8.
Check the flue gas temperature
9.
Check the flue pipe for leaks
10.
Check the soundness of the hot-gas side of the boiler
11.
Enter the fuel used in the corresponding table in the
operating instructions
12.
Provide the system user with information and hand over
all relevant technical documentation
13.
Confirm correct commissioning
Company stamp/signature/date
Tab. 12 Commissioning report
Enter the relevant fuel in the table in the
operating instructions.
Logano GE615 - We reserve the right to make any changes due to technical modifications.
Start up the heating system
Page
page 22
page 27
page 27
page 41
See control panel
documentation
See burner documentation
5
Comments
(signature)
43

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents