Start up the heating system
5.1.1
Creating operating pressure (sealed
heating systems)
On sealed heating systems the pressure gauge marker
must be within the green field.
z Set the red needle on the pressure gauge to the
required operating pressure (at least 1 bar pressure).
z Only fill the system via a WRAS approved method.
z Vent the heating system during filling.
5.1.2
Setting the capacity (open vented heating
systems)
In open systems, the hydrometer needle must lie within
the red field.
z Set the green needle on the hydrometer to the required
capacity.
z Top up the heating water or drain via the boiler fill and
drain valve until the required capacity has been
reached.
5.2

Start up the control panel

Please see the accompanying technical documentation
for the 4000 series control panel for information about on
how to start it up.
5.3

Commission the burner

z When commissioning the burner, follow the
instructions in the technical documentation enclosed
with the burner.
z Fill out the burner commissioning report.
42
Fig 58 Pressure gauge for sealed systems
1
2
3
Fig 59 Hydrometer for open systems
1
2
3
Logano GE615 - We reserve the right to make any changes due to technical modifications.
Red needle
Pressure gauge needle
Green field
Hydrometer needle
Green needle
Red field
6304 4901-04.0K

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents